Almost half the overall projects costing at least Rs 150 crore (Rs 1.5 billion) are facing a time lag as on March 31. Of 558 projects, 272 were running late when FY13 came to an end, official data showed.
As many as 59 of these projects reported delays just in March 2013 (additional delays compared to figures shown in February 2013).
In fact, mega projects costing Rs 1,000 crore or above also saw additional delays in 25 projects, data released by the Ministry of Statistics and Programme Implementation revealed.
The Cabinet Committee on Investments was set up to expedite clearances for mega projects in both government and private enterprises.
According to MoSPI, the reasons for delays are hurdles in land acquisition, forest clearance, equipment erection, supply of material and change in scope of work, among others.
The worst-hit sector among all is roads and highways, in which almost 60 per cent of projects were delayed. Out of 149 projects in this sector, 89 are delayed.
Of this, 17 were additionally delayed, of which two were mega projects. In the petroleum sector, out of 67 projects, 36 were delayed. This means almost half the projects are backlogs.
Of this, 10 projects were additionally delayed.
Further, more than half of 101 projects in the power sector faced time overrun.
In power sector, the highest number of mega projects, nine, were additionally delayed in March.
A senior official said there is a tendency to take too many projects for various reasons, including political, and then there are insufficient funds to spend.
He added if there are some projects that are not economically viable, the Centre should drop these.
The cost overrun in overall central sector projects costing at least Rs 150 crore (Rs 1.5 billion) has reached whopping Rs 1.40 lakh crore (Rs 1.4 trillion) as on March 2013 at Rs 9.29 lakh crore (Rs 9.29 trillion).
This is 17.7 per cent more than the original cost of Rs 7.89 lakh crore (Rs 7.89 trillion).
In March 2012, the cost overrun was 1.19 lakh crore (Rs 1.19 trillion), 16.5 per cent of the original cost in that month. Interestingly, some of the data still remained under-reported, which means the cost and time overrun could head further up.
“Project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggest time/cost overrun figures are under-reported,”
Meet the new ministers in Union Council
Soon, Starbucks at hospitals, schools, corporate campuses
Delay in allocation of gas hits power sector
Oscar Fernandes' plans for the transport sector
RBI seeks faster clearances of projects for high growth