A Business Standard analysis of the status of equipment order placement and the time required for commissioning of power units reveals the 12th Plan’s capacity target of 88,537 Megawatt is likely to be met with only minor slippages.
The good news is that within the first 14 months, orders for manufacturing and commissioning of the entire 88,537 Mw capacity for the 12th Plan have been placed, according to the Central Electricity Authority, the country’s apex power planning body.
For comparison, full order placement had taken more than two years in the last Plan period.
“We are much better placed in the current Plan period, compared to the 11th Plan, because orders for a bulk of the capacity had been placed in the last Plan itself.
At least 40,000 Mw will be added by March next year, giving us the confidence of meeting the target this time,” a senior CEA official said.
Delays in placement of orders have been identified as the chief reason for slippage of power capacity targets in five-year Plans in the country, followed by delays in supply by equipment manufacturer Bharat Heavy Electricals Ltd.
Other reasons include fuel constraints and delayed clearances, according to the power ministry’s National Electricity Plan document.
The country has already added 20,622 Mw in the first year of the current Plan period (2012-13) and an additional 1,852 Mw in the first two months of the current financial year.
So, a total of 22,474 Mw capacity -- or 25 per cent of the Plan target -- was already added in the first 14
IIP data BUNGLING: India's chief statistician explains
Markets remain higher, IT & auto shares gain
Tata Power's nimble steps see lower equity investment
Imported coal to now make power costlier
R-Power's tariff earnings hinge on commission date