Delayed clearances for coal blocks, as well as companies’ own failure in developing mines, appear to have had a financial implication of Rs 1.46 lakh crore (Rs 1.46 trillion) for the country.
The figure has been arrived at by adding the actual loss the country has incurred in partly making up for the production shortfall -- by importing more expensive coal from other countries -- and the opportunity loss due to non-generation of electricity because of coal crunch over the past five years.
According to consultancy firm KPMG, the total loss of output from captive coal mines over this period has been 394 million tonnes (mt)-based on delays with reference to a normative time of 54 months for developing allocated mines.
Of this, 200 mt shortfall has been substituted with imported coal. Assuming the delivered cost of imported coal at Rs 3,980 a tonne and that of domestic coal for a port-based plant at Rs 2,380 a tonne, the additional cost on imported coal works out to Rs 1,600 a tonne -- Rs 32,000 crore (Rs 320 billion) for 200 mt imported coal.
Since 194 mt of coal shortage could still not be made up for, the electricity-generation opportunity lost due to this -- assuming 0.68 kg coal consumption for generating every unit (1 kWh) -- would have been to the tune of 285.2 billion units.
Further, considering the average cost of power at Rs 4 a unit, the total value of lost generation comes to Rs 1.14 lakh crore (Rs 1.14 trillion).
Putting the two figures together, the total loss due to captive mining shortfall, in value terms, come to a staggering Rs 1.46 lakh crore (Rs 1.46 trillion).
Power project delays put Rs 1 lakh cr of loans at risk
Market falls flat: F&O rollovers ahead
Diesel prices to be deregulated in 6 months: Moily
Why you must include PPF, tax-free bonds in portfolio
Multiplex operators strike gold in Bollywood-mad India