In its report for the year ended March 2012, presented to the state Legislature today, the CAG said Rs 43,270 crore was spent by the water resources department on 426 incomplete projects.
In 242 of the 426 incomplete projects, it said the initial budget rose to Rs 33,832 crore from Rs 7,215 crore, up 369 per cent. This resulted in cost overrun of Rs 26,617 crore.
“Though these irrigation projects commenced five to 45 years ago, they are not yet complete. The oldest being Kudki project, in respect of which the year of commencement was 1967, with a target date of completion in five years (1972).”
The CAG’s observations come at a time when the Maharashtra government-appointed special investigation team, led by water expert Madhav Chitale, is looking into the multi-crore irrigation scam, in which more than 36 irrigation projects in the Vidarbha region remain incomplete, with a cost overrun of Rs 26,000
BJP, CPI trash JPC report, call it cover up exercise
Playing the alliance game
Behind-the-scenes: How I-T dept is catching tax evaders
Arvind Kejriwal ends two-week long hunger strike
RIL agrees to CAG audit: Oil Secretary