"The 5 million tons a year liquefied natural gas terminal (adjacent to the 1,940 megawatt power plant) is mechanically complete," a company official said on the sidelines of the Petrotech-2010 oil and gas conference in New Delhi.
"The terminal will be commissioned by this month end."
But since dredging and construction of breakwater facility is not yet complete, the terminal will be commissioned through smaller ships thereby leading to only 30-40 per cent capacity utilisation.
Dredging of the sea-channel leading to the Dabhol terminal is likely to be completed by end of 2011 but the construction of a breakwater that will guard ships against high tides, was not likely before 2013-14.
The LNG terminal will become fully operational only after the completion of the breakwater facilities.
"For the time being, commissioning of the terminal will be achieved through spot cargoes and thereafter, LNG will be sourced through regular tie-up
The power plant currently runs on 8.5 million standard cubic meters per day of natural gas supplied from Reliance Industries' eastern offshore KG-D6 fields.
State-owned gas utility GAIL and power generator NTPC own 29.65 per cent equity stake each in RGPPL while 15.71 per cent is with Maharashtra State Electricity Board.
The remaining stake is with financial institutions (IDBI 9.4 per cent, State Bank of India 7.65 per cent, ICICI Bank 6.3 per cent and Canara Bank 1.65 per cent).
Dabhol plan in limbo due to inadequate gas supply
Qatar soon to be world's top LNG producer
NTPC-BHEL JV looking for global tech partner
ICICI Bank to focus on home loans
Management lessons from ICICI Bank's KV Kamath